CHECKLIST


  • Are the access routes free and easy to access for cranes and the counterweight trailers?
  • Are the roads paved?
  • Can the slope be taken? What is the angle of inclination?
  • Are the roads sufficiently wide?
  • Are there any obstacles: hindrance, traffic signs, bridge (limited tonnage)?
  • Any obstacles on a height: cables, bridges, trees, and tunnels?
  • High/low-tension cables?
  • Height?
  • Maximum bend? Is it compatible as per crane turning radius or is road widening required?
  • Assembly of the jib?
  • Is there enough space for the assembly of the jib?
  • Is there enough space for the assembly of the crane?
  • Is a diversion necessary?
  • Necessary to close the escape routes?
  • Is there enough space for the erection of the crane?
  • Is full outrigger base possible?
  • Can counterweight trailer be parked next to crane?
  • Can the crane lift and put down its own counterweights?
  • Can the crane rotate 360°?
  • If there are restrictions, are they an obstacle?
  • How many cranes on the same spot?
  • Can the main boom rotate without hindering another?
  • Tower cranes on the same site? What is there height and radius?
  • Is the erection area paved?
  • "Proofs of pressure" or probes?
  • What is the maximum permitted ground pressure?
  • Underground pipes: sewer-pipes, high-tension cables?
  • Underground pits, collection mains?
  • Any determination of visible damage before the start of works?
  • Supply of partitions, steel planking, sand-beds?
  • Check the difference in height between the outriggers?
  • Can the charge be supplied in a horizontal way?
  • What is the maximum permissible wind speed?
  • Direction of wind?
  • Is the proper weight of load to be lifted known?
  • What is the load bearing capacity of the ground?
  • Can the ground sustain crane outrigger loads?
  • Should any area need clearance before lifting the load?
  • Are these items inspected and is the certificate of inspection still valid?
  • A need for special hoisting materials?
  • Spreader?
  • Lifting beam?
  • Frame?
  • Others?
  • Fits the hoisting material in the lifting lugs or the fixing points?
  • Can the attachment happen on the ground floor?
  • Second crane with cage? Aerial or scaffolding?
  • Can the hoisting material be removed?
  • Or do you need a second crane with cage? Aerial or scaffolding?
  • Who manipulates the load?
  • Trained people to perform this task?
  • Can the crane driver see the load?
  • Radio contact between crane driver and rigger?
  • Limitation in power and frequency?
  • Detonation free area?
  • Who gives directions to the craned driver?
  • Who is the foreman - rigger?
  • Need a permit before ‘start of works’? Where and when will the permit be issued?
  • Any specific safety measures?
  • Is there a need to close emergency exits?
  • Is there a need for a deviation?
  • To invite all parties involved to a toolbox meeting?
  • Is there a need for special Personal Safety Equipment?
  • Can the works be executed during standard working hours?
  • Information given by the main boom Working Height Limiter?
  • Information given by the main boom Rotation Limiter?
1800-222-909